NEW QUESTION # 24
How can you completely block a material for procurement in a plant? Note: There are 2 correct answers to this question.

  • A. Create a blocking entry in the supplier master record.
  • B. Use a relevant plant-specific material status in the material master.
  • C. Create a quota arrangement entry with a quantity of zero.
  • D. Create an entry in the source list with a blocking indicator and NO supplier.

Answer: A,B


NEW QUESTION # 25
For which of the following business scenarios does a situation template exist in Situation Handling? Note: There are 2 correct answers to this question.

  • A. A purchase order approval is pending.
  • B. The due date for a blocked invoice has passed.
  • C. A supplier confirmation is pending.
  • D. A contract is ready as a source of supply.

Answer: C,D


NEW QUESTION # 26
At what level do you maintain the Automatic PO indicator in the material master?

  • A. Plant
  • B. Client
  • C. Company code
  • D. Purchasing organization

Answer: A


NEW QUESTION # 27
You use quota arrangements. You include a new supplier in an existing quota system. How can you ensure that the new supplier is considered as if they had been part of the quota arrangement from the beginning?

  • A. Manually update the quota.
  • B. Manually update the source list.
  • C. Manually update the quota base quantity.
  • D. Manually update the quota-allocated quantity.

Answer: C


NEW QUESTION # 28
Goods from a supplier arrive at your warehouse. You do NOT want these goods to be part of your inventory yet. What is the procedure for recording the conditional goods receipt (GR)?

  • A. Set the Origin Acceptance flag in the PO item and post a GR to valuated GR blocked stock.
  • B. Post a goods receipt to non-valuated GR blocked stock.
  • C. Select the blocked stock stock type when posting the goods receipt.
  • D. Make a note in the PO and wait until the conditions for accepting the delivery are met.

Answer: B


NEW QUESTION # 29
What can you control with a document type in purchasing? Note: There are 3 correct answers to this question.

  • A. Reference to purchase requisitions
  • B. Confirmation control
  • C. Item number interval
  • D. Allowed account assignment categories
  • E. Number range

Answer: A,C,E


NEW QUESTION # 30
You want to create a purchase document for several minor repairs that may occur over a period of time. They should NOT exceed a total amount in this period. Further details are NOT available.
Which type of purchasing document is best suited for this purpose?

  • A. Invoicing plan
  • B. Release purchase order
  • C. Blanket purchase order
  • D. Service purchase order

Answer: C


NEW QUESTION # 31
You post an invoice with invoice reduction. What can you observe in the system? Note: There are 2 correct answers to this question.

  • A. Two accounting documents are created: one for the invoice posting and one for the credit memo posting.
  • B. Only one accounting document is created containing both the invoice and the credit memo postings.
  • C. The invoice is blocked for payment until the supplier confirms the credit memo receipt.
  • D. A message is created that can be issued to the supplier as a notification of a credit memo posting.

Answer: A,D


NEW QUESTION # 32
You want to create a purchase order. An info record is available for the material-supplier combination. What logic does the system use to determine a price from the info record? Note: There are 2 correct answers to this question.

  • A. The system always proposes the price from the last purchase order, if available.
  • B. If there are NO valid conditions, the system can propose the price from the last purchase order, if available.
  • C. The system always proposes the price stored at purchasing organization level, if available.
  • D. The system always proposes the valid plant-specific price, if available.

Answer: B,D


NEW QUESTION # 33
What are the prerequisites for carrying out material requirements planning (MRP) for a plant? Note: There are 2 correct answers to this question.

  • A. Maintain MRP data in the material master record for the materials to be planned automatically.
  • B. Assign each storage location of the corresponding plant to an MRP area in Customizing.
  • C. Maintain plant parameters for the corresponding plant in Customizing.
  • D. Maintain planned independent requirements for the materials in the plant.

Answer: A,C


NEW QUESTION # 34
Which business partner categories can you choose when creating a new business partner? Note: There are 3 correct answers to this question.

  • A. Group
  • B. Customer
  • C. Person
  • D. Organization
  • E. Supplier

Answer: A,C,D


NEW QUESTION # 35
At which of the following organizational levels must you maintain a business partner master record for a supplier? Note: There are 3 correct answers to this question.

  • A. Client
  • B. Purchasing group
  • C. Purchasing organization
  • D. Plant
  • E. Company code

Answer: A,C,E


NEW QUESTION # 36
How can you automatically update the pricing conditions in a purchasing info record?

  • A. Select the Info Update indicator when maintaining a quotation.
  • B. Select the Info Update indicator when creating a contract release order.
  • C. Select the Info Update indicator when creating a purchase order.
  • D. Select the Info Update indicator when maintaining a contract.

Answer: A


NEW QUESTION # 37
Which situations lead to an open item on the GR/IR clearing account? Note: There are 2 correct answers to this question.

  • A. The delivered quantity for a purchase order item is more than the invoiced quantity.
  • B. The ordered quantity for a purchase order item is more than the invoiced quantity.
  • C. The ordered quantity for a purchase order item is more than the delivered quantity.
  • D. The invoiced quantity for a purchase order item is more than the delivered quantity.

Answer: A,D


NEW QUESTION # 38
What data does the system require to determine the safety stock during automatic reorder point planning? Note: There are 3 correct answers to this question.

  • A. The storage costs code
  • B. Minimum and maximum stock levels
  • C. Service level
  • D. Mean absolute deviation
  • E. Replenishment lead time

Answer: B,D,E


NEW QUESTION # 39
What are some properties of the organization structure for procurement? Note: There are 3 correct answers to this question.

  • A. A plant can only belong to one company code.
  • B. A plant can be assigned to several clients.
  • C. A storage location key must be unique in a company code.
  • D. A storage location can only belong to one plant.
  • E. Several storage locations may be assigned to a plant.

Answer: A,D,E


NEW QUESTION # 40
How does SAP Fiori achieve the role-based design principle? Note: There are 2 correct answers to this question.

  • A. By decomposing big transactions into several discrete apps suited to the user's role
  • B. By separating transactional and analytical apps in different business roles
  • C. By giving end users exactly what they need for their work
  • D. By defining SAP Fiori apps that users can tailor exactly to their needs

Answer: C,D


NEW QUESTION # 41
Which of the following are features of a scheduling agreement? Note: There are 3 correct answers to this question.

  • A. A scheduling agreement can be used for a consignment process.
  • B. A material master record is optional in a scheduling agreement item.
  • C. Item category M (Material unknown) can be used in a scheduling agreement.
  • D. Scheduling agreement delivery schedule lines can only be created manually.
  • E. A scheduling agreement item is always plant-specific.

Answer: A,B,E


NEW QUESTION # 42
Blocking reason Quality is set for an item in an invoice. What could be the reason for this? Note: There are 2 correct answers to this question.

  • A. Goods-receipt-based invoice verification is NOT used and the item in the invoice has the Post to Inspection Stock flag set in its material master.
  • B. Goods-receipt-based invoice verification is used and NO usage decision has been made for the inspection lot for the item in the invoice.
  • C. Goods-receipt-based invoice verification is used and NO goods receipt has been posted for the item in the invoice.
  • D. Goods-receipt-based invoice verification is NOT used and NO usage decision has been made for any inspection lot for the item in the invoice.

Answer: B,D


NEW QUESTION # 43
What must you do when using supplier consignment? Note: There are 2 correct answers to this question.

  • A. Settle liabilities resulting from consignment stock withdrawals.
  • B. Create consignment storage locations.
  • C. Create consignment info records.
  • D. Settle liabilities resulting from consignment stock receipts.

Answer: A,C


NEW QUESTION # 44
Where does SAP S/4HANA store the low-level code used to determine the sequence in which materials are planned during the MRP run? Note: There are 2 correct answers to this question.

  • A. Production version
  • B. Material master
  • C. MRP planning file
  • D. Bill of material

Answer: C,D


NEW QUESTION # 45
Which of the following can you control with the confirmation control key? Note: There are 2 correct answers to this question.

  • A. The document type for the goods receipt
  • B. Default reminder levels for outstanding confirmations
  • C. Whether a confirmation is a prerequisite for a goods receipt
  • D. The sequence of required confirmations

Answer: C,D


NEW QUESTION # 46
Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two suppliers can only supply 1000 pieces at once. What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier? Note: There are 2 correct answers to this question.

  • A. Assign the indicator for quota splitting to the lot-sizing procedure being used.
  • B. Set a maximum lot size in the quota arrangement item and activate the 1x checkbox.
  • C. Set a maximum quota quantity in the quota arrangement item for each supplier.
  • D. Assign a rounding profile in the material master record of the planned material.

Answer: B,C


NEW QUESTION # 47
What needs to be configured and assigned if pricing conditions in purchase orders should only be visible to certain users?

  • A. User parameter EFB
  • B. Field selection key for the activity category
  • C. Field selection key for the transaction
  • D. User parameter EVO

Answer: A


NEW QUESTION # 48
Production planning and product costing are to be implemented in your company. Which organizational level must you choose for stock valuation?

  • A. Controlling area
  • B. Business area
  • C. Plant
  • D. Company code

Answer: A


NEW QUESTION # 49
......

C_TS452_2021 Questions PDF [2024] Use Valid New dump to Clear Exam: https://www.vceprep.com/C_TS452_2021-latest-vce-prep.html