NEW QUESTION 16
What type of programme may also be referred to as a 'must do' programme?

  • A. Emergent
  • B. Compliance
  • C. Vision-led
  • D. Portfolio

Answer: B

 

NEW QUESTION 17
Which of the following statements about a vision-led programme is true?
1. Tends to be top down in approach, with cross functional implications
2. Evolves from concurrent projects

  • A. Only 2 is true
  • B. Both 1 and 2 are true
  • C. Neither 1 or 2 is true
  • D. Only 1 is true

Answer: D

 

NEW QUESTION 18
Which is an assurance management technique?

  • A. Change control
  • B. Issue management
  • C. Gated reviews
  • D. Quality management

Answer: C

 

NEW QUESTION 19
In which perspective are risks MOST likely to be found if a transition is not properly managed and resourced?

  • A. Programme
  • B. Operational
  • C. Strategic
  • D. Project

Answer: B

 

NEW QUESTION 20
Which risk management perspective is concerned with a programme's interdependencies with other initiatives?

  • A. Strategic
  • B. Programme
  • C. Project
  • D. Operational

Answer: A

 

NEW QUESTION 21
Which characteristic describes management rather than leadership?

  • A. It clarifies the current state and the vision of the future
  • B. It resolves the tension between the current state and the vision
  • C. It is always required in a business-as-usual context
  • D. It is most effective when influencing people face-to-face

Answer: A

 

NEW QUESTION 22
Which is a response option to an identified threat?

  • A. Identify the tranche in which it might materialize
  • B. Accept the risk
  • C. Assign responsibility for it to the Programme Manager
  • D. Adjust the risk appetite

Answer: C

 

NEW QUESTION 23
Which role focuses on monitoring the progress of the programme at a strategic level?

  • A. Senior responsible owner
  • B. Programme manager
  • C. Risk manager
  • D. Sponsoring group

Answer: B

 

NEW QUESTION 24
Which is a trigger for a compliance programme?

  • A. The organization chooses to take a new innovative approach to product development
  • B. The organization has to change to meet requirements of new legislation
  • C. A number of stand-alone projects would benefit from better coordination
  • D. The corporate board has created a vision for change

Answer: B

 

NEW QUESTION 25
What programme role is MOST likely to also have a role within a project board to represent the interests of the business?

  • A. Programme Board
  • B. Programme Manager
  • C. Business Change Manager
  • D. Programme Office

Answer: A

 

NEW QUESTION 26
What can programme leaders do to influence key stakeholders?

  • A. Analyze stakeholder influence and interest
  • B. Create a programme communications plan
  • C. Hold visioning workshops to draft the vision statement
  • D. Produce a stakeholder map to show areas of interest

Answer: B

 

NEW QUESTION 27
Which is NOT a purpose of a Blueprint?

  • A. Describe how to get to the future state
  • B. Provide a usable basis for designing the Projects Dossier
  • C. Ensure coherence of the entire future state
  • D. Provide a basis for modelling benefits

Answer: A

 

NEW QUESTION 28
Which information is included in Benefit Profiles?

  • A. Scheduled reviews
  • B. Information audit requirements
  • C. Dependent capabilities
  • D. Procedures to avoid double counting

Answer: D

 

NEW QUESTION 29
Which is a description of a programme resource?

  • A. A process to control a programme
  • B. A logical grouping of projects within a programme
  • C. The objective of a programme
  • D. An input required by a programme

Answer: D

 

NEW QUESTION 30
What term represents the desired state of the organization achieved after transition?

  • A. Output
  • B. Benefit
  • C. Outcome
  • D. Capability

Answer: C

 

NEW QUESTION 31
Which is NOT a reason for Managing the Tranches?

  • A. To maintain information and asset integrity
  • B. To implement the Risk Management Strategy
  • C. To coordinate and manage project delivery
  • D. To maintain focus on stable operations

Answer: B

 

NEW QUESTION 32
Which role is MOST likely to have a focus on managing the costs of training operational teams during transition?

  • A. Senior Responsible Owner
  • B. Programme Office
  • C. Programme Manager
  • D. Business Change Manager

Answer: B

 

NEW QUESTION 33
Which is a programme management principle?

  • A. Vision
  • B. Adding value
  • C. Corporate strategy
  • D. Identifying a programme

Answer: B

 

NEW QUESTION 34
Which is NOT normally a characteristic of a Vision Statement?

  • A. Defines benefits indirectly
  • B. Helps understand the need for change
  • C. Provides basis for development of the Blueprint
  • D. Describes intermediate future states

Answer: A

 

NEW QUESTION 35
In a multiple programme environment, which role may be performed by a 'corporate portfolio board'?

  • A. Programme board
  • B. Sponsoring group
  • C. Programme office
  • D. Design authority

Answer: B

 

NEW QUESTION 36
What role is responsible for tracking the progress of risk responses?

  • A. Risk Manager
  • B. Risk owner
  • C. Design Authority
  • D. Risk actionee

Answer: B

 

NEW QUESTION 37
Which is NOT a governance theme?

  • A. Vision
  • B. Blueprint design and delivery
  • C. The business case
  • D. Benefit profile

Answer: D

 

NEW QUESTION 38
......