Updated Oct-2021 C-ACTIVATE13 Exam Practice Test Questions
Verified C-ACTIVATE13 dumps Q&As 100% Pass in First Attempt Guaranteed Updated Dump
SAP Activate Project Manager Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books | Weighting |
|---|---|---|
| Transition Path "New Implementation SAP S/4HANA On Premise" | Describe concepts, landscape overview and specifics in Workstreams related to implementing SAP S/4HANA On Premise. ACT100 (SAP S/4HANA 1809) | < 8% |
| Transition Path "New Implementation SAP S/4HANA Cloud" | Describe concepts, landscape overview, and specifics in Workstreams related to implementing SAP S/4HANA Cloud. ACT100 (SAP S/4HANA 1809) | 8% - 12% |
| Agile Project Planning | Describe the agile project roles and responsibilities and the preparation of the project including the planning, estimation, user story mapping and construction of backlog. ACT100 (SAP S/4HANA 1809) | 8% - 12% |
| SAP Activate Overview | Define factors influencing SAP Activate, its purpose and place among other frameworks. ACT100 (SAP S/4HANA 1809) | > 12% |
| Transition Path "System Conversion" | Describe concepts, landscape overview and specifics in Workstreams related to “System Conversion” Transition Path. ACT100 (SAP S/4HANA 1809) | < 8% |
| SAP Activate Elements | Provide an overview of content, tools and methodology elements of SAP Activate Solution Implementation Framework. ACT100 (SAP S/4HANA 1809) | > 12% |
| Transition Path "Selective Data Transition" | Describe concepts, landscape overview and specifics in Workstreams related to “Selective Data Transition” Transition Path. ACT100 (SAP S/4HANA 1809) | < 8% |
| Workstreams Overview | Describe concepts, artefact flows, accelerators, tools and roles for each Workstream within SAP Activate Methodology. ACT100 (SAP S/4HANA 1809) | > 12% |
| Agile Project Delivery | Describe how the project team prepares release and sprint plans, and the structure and key activities in each sprint. Discuss key techniques used in agile projects. ACT100 (SAP S/4HANA 1809) | > 12% |
NEW QUESTION 82
Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile approach, what sequence of activities do you perform in the Explore Phase?
Please choose the correct answer.
Response:
- A. a. Set reference value
b. Prioritize initial backlog
c. Conduct Delta Design workshops
d. Conduct Solution Validation workshops - B. a. Conduct Solution Validation workshops
b. Conduct Delta Design workshops
c. Set reference value
d. Prioritize initial backlog - C. a. Conduct Solution Validation workshops
b. Set reference value
c. Prioritize initial backlog
d. Conduct Delta Design workshops - D. a. Set reference value
b. Conduct Solution Validation workshops
c. Prioritize initial backlog
d. Conduct Delta Design workshops
Answer: D
NEW QUESTION 83
What are the responsibilities of the Project Team on level 4 in the picture below?
There are 2 correct answers to this question.
Response:
- A. Set Project policy, standards and oversight
- B. Perform status reporting and communication
- C. Identify and resolve issues and risks
- D. Set business priorities, goals and objectives
Answer: B,C
NEW QUESTION 84
What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices?
Please choose the correct answer.
Response:
- A. Activate and apply SAP Best Practices with SAP Solution Manager
- B. Assemble and apply SAP Best Practices to the system
- C. Activate and apply SAP Best Practices content with the self-service configuration UI
- D. Apply SAP Best Practices with the Configure your Solution application
Answer: A
NEW QUESTION 85
Which activities are part of the Application: Solution Adaption work stream of SAP Activate for new implementations?
There are 3 correct answers to this question.
Response:
- A. Value Audits
- B. Scope Validation
- C. Change Management Plan
- D. Production Support Plan
- E. Value Determination
Answer: A,C,E
NEW QUESTION 86
What are deliverables of the Application: Integration work stream in the prepare phase?
There are 3 correct answers to this question.
Response:
- A. Network Connectivity Checks
- B. Security Checks
- C. Adaptation Specifications
- D. Data Cleansing
- E. Fit/Gap Analysis
Answer: A,B,C
NEW QUESTION 87
What are the benefits of the SAP best practices?
There are 3 correct answers to this question.
Response:
- A. Fast time to value
- B. Fixed organizational structure
- C. Predictable results
- D. Reduced functional scope
- E. Simple on-boarding to cloud
Answer: A,C,E
NEW QUESTION 88
What does SAP Activate recommend to keep team members informed and aligned?
Please choose the correct answer.
Response:
- A. Daily e-mail status updates to project manager
- B. Daily status meeting with project manager
- C. Daily team stand-up meeting
- D. Daily progress review meeting with sponsor
Answer: C
NEW QUESTION 89
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning?
Please choose the correct answer.
Response:
- A. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks
- B. Product Owner's relative estimate of the effort that will be needed to implement the user story
- C. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
- D. Relative estimate in ideal person days that reflects the best estimate provided by the project team
Answer: D
NEW QUESTION 90
Which artifacts in the Testing work stream are created within the Realize phase for the New Implementation of SAP S/4HANA Cloud" transition path?
There are 2 correct answers to this question.
Response:
- A. Reporting Functional Specifications
- B. Functional Specifications
- C. User Acceptance Test - Plan
- D. Functional Test Scenarios
Answer: C,D
NEW QUESTION 91
When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?
Please choose the correct answer.
Response:
- A. During user acceptance testing
- B. During the daily SCRUM meeting
- C. During the sprint review
- D. During the sprint retrospective
Answer: C
NEW QUESTION 92
What does the Side-by-Side Extensibility Option mean?
Please choose the correct answer.
Response:
- A. Have two SAP S/4HANA instances - one for standard code, and another for custom developments
- B. Extensibility based on the SAP Cloud Platform and published APls
- C. Transfer reporting to BW/4HANA
- D. Context-aware SAP S/4HANA extensions, focused on tight integration
Answer: B
NEW QUESTION 93
Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content?
Please choose the correct answer.
Response:
- A. Navigate by RACI matrix accountability
- B. Navigate by work stream
- C. Navigate by Project Team Member Role
- D. Navigate by assigned Delivery Mode
Answer: B
NEW QUESTION 94
Which of the following is not correct about Fit/Gap Analysis?
There are 2 correct answers to this question.
Response:
- A. Drive towards adopting customers processes.
- B. Validate pre-activate and pre-assembled solution in the development system.
- C. Minimize the needs for rework during realization.
- D. Prioritize delta requirement and gaps.
Answer: A,B
NEW QUESTION 95
Which content is made available after you activate SAP Best Practices for a new financial implementation?
There are 2 correct answers to this question.
Response:
- A. Pre-configured business processes
- B. Online help
- C. Implementation Guide
- D. Standard chart of accounts
Answer: A,D
NEW QUESTION 96
What can users do in the Roadmap Viewer tool?
Please choose the correct answer.
Response:
- A. Upload SAP Activate WBS into SAP Solution Manager7.1
- B. Download full SAP Activate methodology content for use off-line
- C. Display and navigate detailed SAP Activate methodology WBS
- D. Create a customer-specific version of SAP Activate Methodology
Answer: C
NEW QUESTION 97
Which activity helps the Project Team add User Stories to the Product Backlog?
Please choose the correct answer.
Response:
- A. Conducting the Solution Validation workshop
- B. Assessing Project Risks
- C. Preparing a Project Schedule
- D. Planning the User Acceptance Test
Answer: A