NEW QUESTION 14
Which of the following belong to the Application Design and Configuration work stream for SAP S/4HANA Cloud in the Explore phase?
There are 2 correct answers to this question.
Response:
- A. Kick-off workshop
- B. Integration prerequisites confirmation
- C. Fit-to-standard workshop
- D. Configuration definition
Answer: C,D
NEW QUESTION 15
What does the Side-by-Side Extensibility Option mean?
Please choose the correct answer.
Response:
- A. Extensibility based on the SAP Cloud Platform and published APls
- B. Transfer reporting to BW/4HANA
- C. Have two SAP S/4HANA instances - one for standard code, and another for custom developments
- D. Context-aware SAP S/4HANA extensions, focused on tight integration
Answer: A
NEW QUESTION 16
In which phase of the SAP Activate Methodology does the team complete the System Assessment?
Please choose the correct answer.
Response:
- A. Prepare
- B. Deploy
- C. Realize
- D. Explore
Answer: A
NEW QUESTION 17
Which Value Chains does SAP Solution Manager 7.2 deliver?
There are 3 correct answers to this question.
Response:
- A. Requirements-to-Deploy
- B. Request-to-Fulfill
- C. Cash-to-Order
- D. Detect-to-Correct
- E. Hire-to-Retire
Answer: A,B,D
NEW QUESTION 18
Which of the following tools are specific to the Data Management work stream? Note: There are 3 correct answers to this question
- A. SAP Landscape Transformation
- B. SAP Solution Manager
- C. SAP S/4HANA Migration Cockpit (for both SAP S/4HANA Cloud and SAP S/4HANA editions)
- D. SAP Data Services
- E. SAP Roadmap Viewer
Answer: B,C,D
NEW QUESTION 19
What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud?
- A. SAP Support Marketplace
- B. SAP Transformation Navigator
- C. Implementation portal for SAP S/4HANA Cloud
- D. SAP Roadmap Viewer
Answer: C
NEW QUESTION 20
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
Please choose the correct answer.
Response:
- A. Prepare
- B. Realize
- C. Deploy
- D. Explore
Answer: C
NEW QUESTION 21
Which of the following are components of SAP Model Company? Note: There are 3 correct answers to this question.
- A. Business-Driven Configuration Questionnaire
- B. Business Process Content for SAP Solution Manager
- C. Quality Gate Checklist
- D. Accelerators
- E. Preconfigured Solution
Answer: A,B,E
NEW QUESTION 22
In which phase do you create a prioritized list of user requirements?
Please choose the correct answer.
Response:
- A. Deploy
- B. Prepare
- C. Realize
- D. Explore
Answer: D
NEW QUESTION 23
Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition?
There are 3 correct answers to this question.
Response:
- A. Sandbox system migration
- B. Delta configuration
- C. Operations impact analysis
- D. Development system migration
- E. Custom code adjustment
Answer: B,D,E
NEW QUESTION 24
In which tools can the project team across the SAP Activate Methodology content including accelerators?
There are 2 correct answers to this question.
Response:
- A. SAP Community Network
- B. SAP Jam
- C. Roadmap Viewer
- D. SAP Service Marketplace
Answer: B,C
NEW QUESTION 25
In which phase will the customer develop a preliminary strategy for building A target operation and support organisational model?
- A. Discover phase
- B. Explore phase
- C. Prepare phase
- D. Run phase
Answer: C
NEW QUESTION 26
Which of the following are part of the 10 SAP quality principle?
There are 2 correct answers to this question
- A. Achieve production readiness
- B. Plan phase at a time
- C. Start scoping early
- D. Use standard functionality optionally
Answer: A,C
NEW QUESTION 27
Why is there NO sandbox system in the "New Implementation of SAP S/4HANA cloud Single Tenant?
- A. Because the customer may use the SAP model company
- B. Because SAP S/4HANA cloud, single tenant edition, contains predefined business
- C. Because the project team uses the DEV system to confirm solution fit
- D. Because the fit-to-standard workshop is conducted using the Q system
Answer: B
NEW QUESTION 28
How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
Response:
- A. Join SAP S/4HANA group on SAP Community Network
- B. Send e-mail to SAP contact address
- C. Submit e-mail address via on-line form
- D. Register on SAP Service Marketplace
Answer: C
NEW QUESTION 29
Which content packages are available in the SAP Package Library?
There are 2 correct answers to this question.
Response:
- A. Rapid Deployment Solutions
- B. SAP Best Practices
- C. SAP Activate Methodology
- D. Solution Builder
Answer: A,B
NEW QUESTION 30
What are some of the key characteristics of the implementation approach in SAP Activate Methodology?
There are 3 correct answers to this question.
Response:
- A. Delta-based
- B. Based on Ready-to-use Content
- C. Cloud Ready
- D. On premise only
- E. Fixed scope
Answer: A,B,C
NEW QUESTION 31
What technique helps a scrum team to prioritize a large, flat backlog?
- A. Planning poker
- B. Fit/gap analysis
- C. User story mapping
- D. Retrospective
Answer: C
NEW QUESTION 32
Which end-to-end turn-key application lifecycle management (ALM) solution can support You in managing requirements and software development for large Agile project.
- A. Change request management
- B. Focused build
- C. Solution manager test suite
- D. Requirement management
Answer: B
NEW QUESTION 33
Which artifacts are part of the solution adoption workstream?
There are 3 correct answers to this question
- A. Business transformation review (point of view)
- B. Project plan
- C. Detailed design-business process
- D. System go live announcement(order)
Answer: A,C,D
NEW QUESTION 34
What are some of the key characteristics of the implementation approach in SAP Activate methodology?
There are 3 correct answers to this question.
- A. Cloud ready
- B. Based on ready-to-use content
- C. ActivaDelta-based
- D. On premise only
- E. Fixed scope
Answer: A,B,C
NEW QUESTION 35
What tool would you use for managing project tasks and solution documentation Who implementing SAP S/4HANA
- A. SAP transformation Navigator
- B. Implementation portal for SAP S/4HANA cloud
- C. SAP roadmap viewer
- D. SAP support marketplace
Answer: B
NEW QUESTION 36
What do you do during an iterative approach to build a solution?
Please choose the correct answer.
Response:
- A. Deliver a prototype of the solution
- B. Build the solution module by module
- C. Provide a working solution only at the end of the release
- D. Include frequent inspection check-points
Answer: D
NEW QUESTION 37
......
2022 Valid C-ACTIVATE13 test answers & SAP Exam PDF: https://www.vceprep.com/C-ACTIVATE13-latest-vce-prep.html